Oval Village, London: Phase-1

Oval Village, London: Phase-1

This project involves the demolition of a former Tesco Superstore and Axis building, the removal of associated hard standings, and the design and installation of a piling mat.
The structural makeups are as follows: Tesco building on Kennington Lane: the structure consists of a steel frame externally clad with insulation composite panels with a large steel cantilever atrium entrance section. Axis structure on Vauxhall Street: the structure consists of a concrete framed, brick clad building.
The demolition methods are a mixture of piecemeal method, hot-work preparation and progressive fragmentation using a demolition rig from a safe working distance, clearing and processing the demolition arising materials; reduce level dig, and clearing the site to a clean and level finish.
What We Did:
  • Produce the Pre-Construction Information
  • Carry out a consultation on the tender list
  • Attend the bid meetings and provide feedback on the submissions
  • Review and approve the RAMS and issue a report
  • Review and approve the asbestos POW and issue report
  • Carry out the pre-start site audit and issue a report
  • Carry out several site audits and issue a report on the progress
  • Carry out the completion site audit and issue a report Produce a H&S File